No. |
Power Station |
Hydro Station Installed Capacity |
Transformation of Content |
Commissioned
Date |
Mw |
1 |
Shanxi Shimen |
3×12.5 |
Technological transformation of the hydraulic turbine |
1985 |
2 |
Guangxi Dahua |
4×114 |
The technological transformation of generator |
1999 |
3 |
Fujian Shaxikou |
4×75 |
Transformation of the trash boom |
2002 |
4 |
Yunnan Lushuihe |
1×17 |
Transformation of the Impulse runner |
2003 |
5 |
Zhejiang Sangang |
2×6.3 |
Overhaul of the unit expansion |
2003 |
6 |
Fujian Shaxikou |
4×75 |
Transformation of the guide apparatus |
2004 |
7 |
Fujian Huaan |
4×10 |
Transformation of the regulating gear |
2004 |
8 |
Fujian Yongkou |
2×25 |
Transformation of the oil feeder |
2004 |
9 |
Yunnan Lushuihe |
1×17 |
Transformation of a set of the hydaulic turbine |
2005 |
10 |
Zhejiang Hunanzhen 4# |
4×50 |
Transformation of the francis runner |
2005 |
11 |
Xinjiang Hongshanzui third level |
4×11 |
The enhancement of runner capacity |
2005 |
12 |
Zhejiang Fengyuang |
4×9 |
The enhancement of hydraulic turbine capacity |
2006 |
13 |
Xinjiang Xidaqiao #1#2 |
4×6.5 |
The enhancement of power supply capacity |
2006 |
14 |
Hubei Baishuiyu |
1×5 |
Overhaul of the unit expansion |
2006 |
15 |
Guizhou Yangtou |
2×8 |
Overhaul of the unit expansion |
2007 |
16 |
Gansu Daxia |
4×75 |
Overhaul of the runner expansion |
2007 |
17 |
Xinjiang Hongshanzui second level |
4×4 |
The enhancement of runner capacity |
2007 |
18 |
Xinjiang Hongshanzui forth level |
4×3.5 |
The enhancement of runner capacity |
2007 |
19 |
Zhejiang Jiangxia Tidal |
3×0.7 |
Technological transformation of the unit |
2009 |
20 |
Hunan Zhujin |
3×1.25 |
The enhancement of runner capacity |
2009 |